OUR PROJECTS

SETON BOSTON PIZZA

October 2018  – November 2018

Seton Boston Pizza

Location: Calgary
Project Status: Complete

Class A Fire Consulting provided a review of the fire alarm drawings and the on-site verification for this project. During the drawing review, we discovered that fire alarm strobes were not included in the accessible washrooms. A change notice was issued, the electrical contractor was able to install the required strobes and the verification was completed.